I’m in commercial construction. Almost everything we use takes 2-3 (what was 6 weeks now 12-18 weeks) times longer to get. Overall commercial building cost is up north of 25%. Pricing for copper & steel up 100% lumber 210%. All this started January 21’. Haven’t figured out what changed in early 21’ that could have caused this …