Guy's,
The slab is going ontop of the level as you look at it.
The builder ses out the job tomorrow, the sparky lays his cables tomorrow, the plumber on Monday, the slab on Tuesday.
The brickie is starting 5-7 days after the slab is layed.
STIFFY
|